This page explains how to request a Building Control site inspection and outlines the notice periods and requirements needed before submitting a request.
To improve our service and ensure compliance with statutory requirements, Breckland Building Control operates a next-day inspection model. This means inspection requests must be submitted with a minimum of 24 hours' notice. Same-day inspection requests can no longer be accepted.
All inspection requests must be submitted by 4:00pm on the previous working day to secure an inspection for the next working day (excluding weekends and bank holidays).
Inspections can only be booked online where a valid Building Regulations application has already been submitted and accepted by Breckland Council.
How to Request an Inspection
If you have an active Building Regulations application with us, please click the link below to book your inspection.
Please note that timed appointments cannot be offered. Our team of surveyors undertake inspections throughout the working day, and your visit may take place at any point during the day depending on scheduling and location.
No Building Regulations Application?
If your project does not yet have a Building Regulations application in place, or you are unsure whether one exists, pleasecontact us using our online form before carrying out further works:
Our team will advise on the correct process, including whether an application is required.